Off-Grid Power For Gebeng AI
TNB Power Generation and Citaglobal Berhad have signed a memorandum of understanding to explore building a dedicated off-grid power supply of up to 1,300 megawatts for a proposed AI data-centre park in Gebeng, Pahang. The third party to the agreement is TIZA AI, which plans to develop the park on Citaglobal’s 247-acre industrial site near Kuantan.
TIZA AI received approval for the park from the Data Centre Task Force in September. A condition of that approval is that the park’s electricity must come from an off-grid supply rather than the national grid. TIZA AI says it is in talks with several hyperscalers and other partners interested in setting up data centres at the site.
Under the plan, TNB’s power generation arm would lead development of the power facilities, and Citaglobal’s New Energy unit would contribute renewable energy and battery storage expertise. The two would develop, own and operate the plants through a joint venture. The supply could combine gas-fired generation, solar power and battery storage, with the final mix to be decided by feasibility studies.
Citaglobal executive chairman Tan Sri Mohamad Norza Zakaria, who also chairs TIZA AI, said Pahang’s land, water, Kuantan Port and the East Coast Rail Link made it well placed to become Malaysia’s next data-centre hub. TNB chief executive Datuk Seri Shamsul Ahmad said energy readiness must keep pace with the growth of the country’s digital economy.
The agreement is valid for one year and does not commit the parties to build the facilities or to buy or sell electricity. Investment, financing, capacity, tariffs and supply terms are still to be agreed, subject to feasibility studies and board, shareholder and regulatory approvals.
Citaglobal Completes Perak Hydro Deals
Citaglobal Berhad has completed its acquisition of 70% stakes in two hydropower assets in Perak, giving its New Energy business control of the operating Slim plant and the Kampar project, which is still under development. The deals were first announced in August 2025.
The two assets have a combined approved capacity of 12.6MW. Each holds a signed renewable energy power purchase agreement with Tenaga Nasional Berhad (TNB) and a feed-in approval from the Sustainable Energy Development Authority. Perak Hydro Renewable Energy Corporation keeps the remaining 30% of each company.
Slim has been selling electricity to TNB since 2019. Under SEDA’s 2026 feed-in tariff round, it has been approved to expand from 6MW to 6.6MW, and its tariff rises to 34 sen per kWh from 25 sen. Management estimates the plant will earn about RM700,000 a month, depending on water flow, and expects it to contribute to group revenue before the end of the year.
The 6MW Kampar project was partly built when the deal was agreed. Its revised approval sets a tariff of 34 sen per kWh for the first 10 years of operation and 32.4 sen for the next 11, up from 24.99 sen.
The completion follows the groundbreaking last month of the 200MW Chereh Floating Solar Project in Pahang, which Citaglobal is developing with Masdar and TIZA Global. On Monday the group also signed a memorandum of understanding with TNB Power Generation and TIZA AI to study a dedicated off-grid power supply for the proposed Gebeng AI Data Centre Park.
GTA, Safran Plan Helicopter Hub
GTA Holdings Berhad has signed a non-binding memorandum of understanding with Safran Helicopter Engines Asia to explore setting up a helicopter engine repair and training centre in Malaysia. The agreement was formalised during French President Emmanuel Macron’s official visit to Malaysia on 16 and 17 November.
The proposed Helicopter Engine Accessory Repair & Training Centre, known as HEART, would be based at the facilities of GTA’s subsidiary Global Turbine Asia. It would repair engine components and provide approved technical training for operators of Safran-powered Airbus helicopters in Malaysia and the wider region.
Under the plan, Safran would explore providing repair know-how, technical data and training, while Global Turbine would assess investment in facilities, tooling, test benches and qualified staff. The two companies intend to set up a joint working group to define the technical scope, milestones and responsibilities.
Global Turbine already maintains the Makila 2A1 engines on the Royal Malaysian Air Force’s H225M fleet and has been a Safran-certified maintenance centre for more than 15 years. GTA says the RMAF’s proposed purchase of four more Airbus helicopters could create further maintenance work, subject to the government’s procurement decision and contract terms.
The partners also plan to put the cooperation forward under the Industrial Collaboration Programme linked to the helicopter purchase, as part of efforts to build local defence expertise. The project still requires technical and commercial talks, regulatory and export approvals, and definitive agreements.
Tex Cycle Revenue Jumps 42%
Tex Cycle Technology (M) Berhad posted revenue of RM25.1 million for the third quarter ended 30 September, up 42% from RM17.7 million a year earlier. Growth came from stronger demand in its recovery and recycling division and from its subsidiary Meridian World. Profit did not keep pace, however. Pre-tax profit was flat at RM2.7 million, and net profit rose 2% to RM2.3 million.
The recovery and recycling division remained the group’s main earner, with revenue up 58% to RM23.8 million. The renewable energy division continued to bring in income from the group’s solar feed-in tariff plant and its corporate renewable energy power purchase agreements.
Compared with the previous quarter, revenue rose 4% from RM24.2 million, but pre-tax profit fell 37% from RM4.3 million because of higher cost of sales. For the first nine months of the year, revenue nearly doubled to RM69.9 million, pre-tax profit rose 27% to RM10.9 million and net profit climbed 22% to RM8.9 million.
Group chief executive Gary Dass said higher operating costs had weighed on profitability. He said the company was focusing on operational efficiency and on making better use of its subsidiaries together.
Tex Cycle plans to expand its oil and gas waste treatment capacity at its Telok Gong facility. It also aims to use Meridian’s expertise to grow in specialised areas such as e-waste and processing high-value waste by-products. The group intends to combine the strengths and customer networks of Meridian and its other subsidiary, Tex Cycle (P2), to win a bigger share of the environmental services market.
Cuckoo Profit Nearly Doubles
CUCKOO International (MAL) Berhad nearly doubled its net profit to RM26.6 million in the third quarter ended 30 September, up 97.1% from RM13.5 million a year earlier. Revenue, however, fell 8.4% to RM242.1 million, which the home appliance and water purifier company blamed on softer consumer demand and fewer units sold.
The profit jump came from wider margins and fewer bad debts. Gross margin rose to 37.1% from 32.1%, helped by lower customer acquisition costs and cheaper products because of the stronger ringgit. Losses on impairment of financial instruments fell 37.7% to RM18.3 million, which the company said reflected better repayment by customers after it tightened credit checks in July 2025.
For the first nine months of the year, net profit rose 16.1% to RM79.7 million, while revenue came in at RM715.9 million. The company also cut its borrowings to RM84.4 million from RM139.6 million at the end of last year, and generated RM78.3 million in operating cash flow.
Chief executive KC Hoe said the results showed the business was resilient despite cautious consumers. He said the improvements in margins, cost control and customer repayments were encouraging.
After the quarter ended, CUCKOO launched an Associate Sales Partner programme on 1 October, signing four independent businesses to sell its products through their own sales teams. The company said it was cautiously optimistic about the rest of the year despite a challenging operating environment.
Samaiden, Parkland Eye 1,000MW Renewables
Renewable energy firm Samaiden Group Berhad has signed a memorandum of understanding with Parkland Renewable Energy to explore renewable energy projects with a combined capacity of up to 1,000 megawatts in Peninsular Malaysia. Parkland Renewable Energy is a joint venture owned 60% by property developer Parkland Berhad and 40% by a subsidiary of Hong Kong-listed Xinyi Energy Holdings.
The projects would be developed under the Corporate Renewable Energy Supply Scheme (CRESS), which lets companies buy green electricity directly from producers through the national grid. They could be built at one site or several, and in phases, depending on feasibility studies, approvals and finding corporate buyers for the power.
Under the agreement, Samaiden will handle feasibility assessments, design and technical planning, and is named as the exclusive engineering and construction contractor. Parkland will be responsible for finding and securing land and obtaining development approvals. Both parties will look for corporate customers and negotiate supply deals.
Samaiden group managing director Datuk Chow Pui Hee said growing pressure on businesses to cut emissions was creating more opportunities under CRESS. Parkland group managing director Datuk Tan See Sen said renewable energy would give the township developer an additional source of recurring income, building on its 99.99MW solar project in Tangkak, Johor.
The agreement lasts 12 months and can be ended by either side with 30 days’ notice. It does not commit either party to invest, acquire land or sign final agreements. Capacity, financing and revenue-sharing terms are still to be agreed.
KEB Opens Flat On Debut
Property developer KEB Berhad made its debut on the ACE Market of Bursa Malaysia on Monday, opening at RM0.35, unchanged from its initial public offering price. The company trades under the stock code 0481.
KEB raised about RM48.49 million in the IPO by issuing 138.54 million new shares, giving it a market capitalisation of about RM308.83 million at the offer price. It plans to spend RM19 million on buying land, RM14.89 million on working capital for its projects, RM8.5 million on repaying bank borrowings and RM6.1 million on listing expenses.
The company has been developing residential, industrial, commercial and mixed-use property since 2004, and has completed 14 projects. It has four developments under way with an estimated gross development value of RM1.36 billion, and two future projects worth about RM382.73 million. It also holds about 60 acres of land for future development.
KEB has its own construction arm, KEB Utama, a CIDB Grade G7 contractor, which it says gives it more control over the quality and timing of its projects.
Managing director Datuk Lim Kim Chong said the listing was a significant milestone and put the company in a stronger position to expand its landbank and fund its developments. M & A Securities was the principal adviser, sponsor and underwriter for the IPO, and Eco Asia Capital Advisory was the financial adviser.
Media & PR: editor@dailystraits.com. Copyright 2021–Present DailyStraits.com. All rights reserved.